The key stakeholders of a project would like to be actively involved in the review...

The key stakeholders of a project would like to be actively involved in the review of product increments.

What should the project manager do?

A.

Analyze their interest and influence to manage expectations.

B.

Update the communications management plan for key stakeholders.

C.

Identify the needs and expectations of key stakeholders.

D.

Encourage their participation in release and sprint reviews.