Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

The change control board (CCB) rejects a change request submitted by a subject matter expert...

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?

A.

Requested that the sponsor approved the change request first.

B.

Assessed the change's overall impact to the project before submission

C.

Ensured that the change request was aligned with the project scope

D.

Submitted the change request directly to the CCB

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"