PMI PMP Question Answer
In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.
What should the project manager do?
Update the issue log and refer to the resource management plan to address the situation.
Ask the team for extra work to fulfill the project commitment.
Reduce the scope of the project and inform stakeholders.