A project team is engaging a development team in another country to develop software.

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.

What should the project manager do?

A.

Travel to the development team's office to push the schedule.

B.

Set up a meeting with key stakeholders to clarify requirements.

C.

Escalate to the project steering committee and request additional time.

D.

Create prototypes with the development team to confirm requirements.