During the planning phase of a project, the local project team presents a task to...

During the planning phase of a project, the local project team presents a task to the project manager. This task will require several months to complete, and the

duration will affect the expected timeline.

What should the project manager do first?

A.

Communicate to stakeholders the updated schedule after considering how long each task will take.

B.

Add more resources during the task execution phase to complete the project on time.

C.

Meet with the project team to assess the task and any possible improvement to reduce its duration.

D.

Procure services to execute the task so the local project team can progress with other project activities.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"