During the execution of an Al project, the different teams responsible for developing deliverables are...

During the execution of an Al project, the different teams responsible for developing deliverables are consistently delayed. The teams do not have access to shared

resources or are dependent on other teams to complete tasks.

What should the project manager do first?

A.

Use project management tools to identify bottlenecks.

B.

Update communication processes to avoid roadblocks.

C.

Meet with the teams involved to identify the root cause.

D.

Meet with the team to prioritize goals to avoid impediments.