Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

During the planning for a long project, the project manager recognized that severalmembers of the...

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

A.

Increase the overall project duration to account for the inexperienced team members

on the project.

B.

Ensure planning has accounted for replacing team members in new project roles who

do not deliver on project goals.

C.

Assess the training requirements and ensure time for professional development

training by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team members

assigned to the project.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"