As a project is reaching completion, the project sponsor tells the project manager toimmediately close...

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?

A.

Ensure that the whole team is appropriately recognized and organize a project farewell

party to celebrate the project success and closure.

B.

Update and close both the risk register and issue log with the latest updates, and save

them in the organization's project management information system (PMIS).

C.

Archive all the project documents following the organization's accepted practices so

the documents can be used in other future projects.

D.

Meet with the project sponsor and advise that the new project might be difficult to

undertake because the current project is not yet complete.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"