Asubject matter expert (SME) working for the client ' s company is coming up with...

Asubject matter expert (SME) working for the client ' s company is coming up with new project requirements periodically. This causes confusion, time is wasted

rearranging the requirements. The project manager has learned that this SME is a new to the project.

What should the project manager do?

A.

Gather the project imperatives from historical project documents.

B.

Update the change management plan with the new requirements.

C.

Review baselined requirements with the SME.

D.

Escalate the issue with the SME and project sponsor.