A project manager is overseeing a multisprint data integration project involving internal developers and an outsourced analytics team. Midway through the second
sprint, the project manager notices signs of reduced engagement: slower response times, vague status updates, and missed handoff deadlines between the two
teams. The initial project management plan includes regular reporting but no formal feedback mechanisms.
What should the project manager do?