A project team is in the planning stage and has prepared a list of activities...

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

A.

Finish to start

B.

Start to start

C.

Start to finish