A company is undergoing a digital transformation and is changing its project portfolio to an...

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"