A project manager is working on an agile project.

A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when the project deliverables are considered complete.

How should the project manager respond?

A.

Items are considered complete when they satisfy the definition of done (DoD).

B.

The scrum master will approve the user stories that are complete.

C.

Backlog items are considered complete when the product owner approves the demo.

D.

At the end of each sprint, the outcome is considered ready for production.