A project manager is newly assigned to the second phase of an ongoing project.

A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.

What should the project manager do first?

A.

Update the risk management plan.

B.

Extend the timeline of the project.

C.

Check the organizational process assets (OPAs).

D.

Acquire knowledgeable resources.