A project manager has recently been assigned to a construction project.

A project manager has recently been assigned to a construction project. The project has hundreds of stakeholders and three stages. The project manager recognizes that many steps have already been started, including risk identification. The project sponsor asks the project manager to rank the risks contained in the register. How should the project manager respond to the request?

A.

Execute a qualitative analysis to provide identified risks prioritization.

B.

Inform that a quantitative risk prioritization was completed using Monte Carlo simulation.

C.

Inform that a qualitative analysis has already been completed.

D.

Perform a quantitative analysis to provide identified risks prioritization.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"