A construction project is in its final stage when the owner of a private property...

A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?

A.

Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.

B.

Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract timeline.

C.

Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.

D.

Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"