A project manager has been given a critical, 5-day window and is allocated a maximum...

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted

a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After

3 days of work, the project manager completed two actions and spent US$80,000.

What should the project manager do next?

A.

As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions.

B.

Stop the work and raise a project change request to the change control board (CCB) for additional funds and a project schedule extension.

C.

As the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0, reevaluate and prioritize the remaining actions.

D.

Complete all actions and then inform the client of the additional cost and schedule overrun needed to complete the project.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"