A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A ' s project manager do?

A.

Allow project B ' s leader to continue building relationships.

B.

Talk with project B ' s leader to discuss possible impacts to both projects.

C.

Tell project A ' s team member to ignore project B ' s leader.

D.

Ensure project A ' s team member can finish the work committed to project A.