A company has assigned a project manager to the initial task of determining the resources...

A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?

A.

Company ' s historical organizational project artifacts

B.

Company ' s project responsibility assignment matrix (RAM)

C.

Company ' s resource management plan

D.

Company ' s resource calendars