Winter Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

A customer's technical lead discussed a new feature with the project manager.

A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.

What should the project manager do next?

A.

Agree with the project team to modify and delete some of the stories in the current sprint backlog

B.

Obtain approval from the project team and add the new story to the product backlog

C.

Receive an agreement from the product owner and add the new story to the product backlog

D.

Negotiate with the scrum master before adding the new story to the sprint backlog

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"