A customer discovered quality issues with the latest deliverables.

A customer discovered quality issues with the latest deliverables. However, the project team immediately resolved the issues.

Now that the project is back on track, what should the project manager do next?

A.

Reassess the risk log to ensure it is up to date.

B.

Monitor quality metrics to ensure the project continues as planned.

C.

Perform lessons learned to ensure the issue does not happen again.

D.

Schedule a team meeting to review the issue,