You work as a Project Manager for Media Perfect Inc.

You work as a Project Manager for Media Perfect Inc. Several projects are running under your supervision. Rick, team leader of a project, provides you performance indexes of his project. The schedule variance (SV) of his project is 25. What does this figure depict?

A.

Project is behind the schedule.

B.

Costs are higher than planned.

C.

Project is right on target.

D.

Project is ahead of the schedule.