You are the project manager of the NAA Project for your organization.

You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project. Which of the following statements is most accurate about fast tracking the project?

A.

Fast tracking only works if activities can be overlapped to shorten duration.

B.

Fast tracking only works if the activities are effort-driven.

C.

Fast tracking only works if the activities are resource-driven.

D.

Fast tracking only works if activities can have start-to-start relationships.