You are the project manager of the NHQ Project.

You are the project manager of the NHQ Project. Management has told you that resource leveling will be enforced on your project, but they still want you to complete the project by July 2. With the current resources you have and the resource leveling imposed, you would not be able to finish by the constraint. What document should you update to address this situation?

A.

Project activity resource requirements

B.

Project schedule management plan

C.

Project scope

D.

Project charter