You are the project manager for your organization.

You are the project manager for your organization. You have created the project schedule and have presented it to the management for their approval. Management decides to enforce resource leveling heuristics on your project schedule. What will likely happen to your project now?

A.

It will require fewer resources due to the cut in the project scope.

B.

It will require additional resources for the additions to the project scope.

C.

It will require additional resources if it is to finish in the same amount of time, as originally predicted.

D.

It will require a new scope baseline to reflect the management change in the project approach.

PMI-SP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-SP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"