Which of the following is an output of the Identify Stakeholders process?
A.
Scope baseline
B.
Project scope statement
C.
Project charter
D.
Stakeholder register
The Answer Is:
D
This question includes an explanation.
Explanation:
The Identify Stakeholders process identifies all people or organizations that are impacted by the project. It also documents relevant information regarding their interests, involvement, and impact on project success. Stakeholder register and stakeholder management strategy are outputs of this process.
Answer option C is incorrect. Project charter is one of the inputs of the Identify Stakeholders process.
Answer option A is incorrect. Scope baseline is one of the outputs of the Create Work Breakdown Structure (WBS) process.
Answer option B is incorrect. Project scope statement is one of the outputs of the Define Scope process.
PMI-SP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"