Nancy is the project manager of a project with 78 stakeholders.

Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to express to her project team and to the management the importance of communication in this project. She would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

A.

78

B.

156

C.

3,003

D.

6,084