Meet with the agile team lead to discuss ways to improve team velocity and get back on track
B.
Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins
C.
In the upcoming retrospective, discuss ways to improve sharing project status information
D.
Meet with the marketing stakeholders to explain that the team will miss the planned release date
The Answer Is:
D
This question includes an explanation.
Explanation:
According to the PMI Agile Practice Guide (Section 7.1 Communication) and PMBOKĀ® Guide (6th Edition, Section 13.3 Manage Stakeholder Engagement), transparency with stakeholders is fundamental in agile environments. Delays or deviations from expected outcomes must be promptly communicated to affected stakeholders to adjust expectations and plans.
Mike Griffiths in the PMI-ACP Exam Prep Book (Chapter 4: Stakeholder Engagement) emphasizes that one of the key values in agile is responding to change over following a plan, and that includes openly discussing risks and delays with impacted parties.
Thus, Option D is correct: the agile coach should proactively engage marketing stakeholders to inform them about the delay and support revised planning.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"