Mark it as incomplete and prioritize it for the next sprint
B.
Mark it as complete, since the product owner has the final say
C.
Discard it and create a new story for the remaining scope of work
D.
Mark it as complete, since the team completed the scope of work
The Answer Is:
A
This question includes an explanation.
Explanation:
According to the PMI Agile Practice Guide (Section 5.3 Sprint Review and Acceptance) and Mike Griffiths’ PMI-ACP Exam Prep Book (Chapter 6: Value-Driven Delivery), stories are only marked complete if they meet the Definition of Done (DoD) and are accepted by the product owner and stakeholders. If the customer (or their representative) raises a legitimate concern during the review, the story should be treated as incomplete until consensus is reached or it meets expectations.
Option A is correct: if the story does not meet customer expectations, it should be reprioritized for the next sprint or refined.
Option B and D incorrectly assume that product owner or team authority overrides customer feedback.
Option C suggests discarding the story, which is inappropriate if the customer still needs the functionality.
Stakeholder feedback is critical in agile, and the goal is delivering value, not simply completing a checklist.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"