Two similar stories A and B are estimated at 3 story points.

Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?

A.

Assign story B more than 8 story points to provide a better estimate

B.

Add points to story B’s iteration to account for the error but keep story B at 3 points

C.

Assign more resources to story B to bring it in line with the estimate

D.

Reestimate all stories including values for A, B, and C