A user story that is too large to complete in one sprint is considered anepic. Agile teams shouldsplit it into smaller, valuable, testable stories. ThePMI Agile Practice Guide (Section 5.2: User Stories and Decomposition)andMike Griffiths’ PMI-ACP Exam Prep Book (Chapter 6: Adaptive Planning)recommendbreaking down large storiesand renegotiating sprint scopecollaborativelywith the product owner.
Option Cis correct: this aligns withcollaborative planning and story decomposition.
Option Ais rigid and dismisses collaboration.
Option Bpromotes unsustainable practices.
Option Dviolates the principle offixed-length iterations.