An employee just received an Agile certification and has been promoted to team leader.

An employee just received an Agile certification and has been promoted to team leader. They are working on a project that is experiencing issues with late deliverables. After monitoring project progress, they notice that one impediment is continuously repeated at start of each phase, affecting team's productivity.

How should the team leader exhibit servant leadership?

A.

By being a change agent

B.

By being the authority on processes

C.

By being a coach

D.

By removing impediments