Midway through an iteration, an agile team learns that a team member will be unavailable...

Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?

A.

Raise an impediment that resource tasks will be blocked and notify the Product Owner

B.

Ask the delivery manager for a temporary resource

C.

Ask the Scrum Master to assign that team member's tasks to the next available resource

D.

Assume the team member's tasks to meet iteration goals and notify the Product Owner