The correct answer is D – Meet with project stakeholders to review the backlog and determine if the scope should be adjusted. Agile emphasizes continuous stakeholder collaboration and delivering maximum value. If the remaining backlog may not contribute significant value, it’s prudent for the Product Owner to reassess scope and validate changes with stakeholders.
From the PMI Agile Practice Guide:
“Engage stakeholders continuously to review priorities and business value. If the product delivers sufficient value earlier than anticipated, the scope may be reduced or the project closed.”
(PMI Agile Practice Guide, Section 3.4 – Value-Driven Delivery)
Mike Griffiths adds:
“Early delivery of value allows teams to stop work that no longer serves business objectives. This requires transparent communication with stakeholders to validate scope adjustments.”
(Mike Griffiths, PMI-ACP Exam Prep, Chapter 3 – Value-Driven Delivery)
Incorrect options:
A assumes authority without consulting stakeholders.
B doesn’t address the possible need for scope reduction.
C skips stakeholder validation before deployment decisions.
Answer: D
────────────────────────────────────