During a project review, the team discovers customer feedback that would add scope.

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate