A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).
At the end of which sprint will the minimum viable product (MVP) be completed?

Accessibility – color blind → 4 story points
Increase security → 21 story points
Add AI chatbot → 5 story points
The risk register mentions a reduction of 1 story point per sprint from sprints 4 through 6 due to the holiday schedule.
If we assume the team ' s normal velocity is 10 story points per sprint (hypothetically), it would drop to 9 story points per sprint for sprints 4-6.