What should a team do when they complete all sprint goals earlier than expected?
Begin working on an item in the backlog
Ask the scrum master to select an item from the backlog on which to work
Ask the product owner to select an item from the backlog on which to work
Jointly decide with the scrum master on an item from the backlog on which to work