PMI PMI-002 Question Answer
Decomposition is ___________.
What happens when changes to the project scope are ignore
Subdividing the major project deliverables into smaller, more manageable components
Defining a general product description into more discrete definitions of individual components
Subdividing the project into logical divisions of effort aligned within the performing organization's functional areas