PMI PMI-002 Question Answer
A contingency plan is executed when _______.
A risk is identified
An identified risk occurs
When a workaround is needed
All of the above
B is the correct answer. A contingency plan is executed when An identified risk occurs
TESTED 19 Oct 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved