Which of the following contract types would be most beneficial to both parties in cases...

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials