A project manager has decided to wait until all requirements are developed to initiate testing.

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

A.

Start-to-finish

B.

Finish-to-finish

C.

Finish-to-start

D.

Start-to-start