A project manager is conducting an evaluation of a product to determine whether it is...

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report