You are the program manager of the HNG Program.

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?

A.

-$85,230

B.

$821,065

C.

-$284,100

D.

-$117,295