Which of the following statements are true regarding program scope changes? (Choose three.)
Scope changes may originate from the stake holders.
Change requests for a particular project have to be approved by the project manager irrespective of their potential impact on multiple projects.
The program has a change control board that analyzes changes at the program level.
The change control process on a program is often hierarchical.