Company A acquires company B, which leads to a two-year program to integrate the processes...

Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company’s staff is unhappy about the acquisition. As a result, company B’s project team fails to provide status and cost data in a format that conforms to the program standards.

What should the program manager do first?

A.

Inform the stakeholders of this issue as soon as possible

B.

Change the program standards, aligning them with the project standards

C.

Work with the reports provided to extract the required information

D.

Remind the project manager of the relevant program standards

PgMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PgMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"