A program with 10 components is in the planning phase.

A program with 10 components is in the planning phase. Project managers who oversee the component projects request detailed schedules. These schedules will be merged into one document to create a master schedule.

What should the program manager do to ensure that the overall program life cycle will meet stakeholder needs and deliver planned benefits?

A.

Establish a quality review for the project schedules to ensure that resource leveling and baselines are followed and component projects are delivered on time

B.

Work with the project managers to decompose their schedules to minimize risk and better understand the dependencies and resource needs

C.

Decompose the component schedules to determine if work can be executed more quickly to deliver value earlier than planned

D.

Create a work breakdown structure (WBS) to align program execution with stakeholder expectations and the benefits management plan

PgMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PgMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"