A two-year program is coming to an end.

A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts or left the company. Several new members have joined, but have a short association with the program, which changes the board’s expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.

How should the program manager handle this situation?

A.

Review the final program outcome with the program sponsor

B.

Prepare a program change request utilizing new board member input

C.

Review the strategic plan and benefits management plan with the board

D.

Present the final program status, costs, and schedule reports

PgMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PgMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"