Which occurs when the P3O implementation programme is closed?
A.
Vision Statement is to reflect delivery
B.
Blueprint is produced to document processes
C.
Risks to the implementation are captured
D.
P3O capability becomes business as usual
The Answer Is:
D
This question includes an explanation.
Explanation:
The P3O® Foundation (2013) manual states that when the P3O implementation programme closes, the P3O capability becomes business as usual. Section 4.4.5 notes, "Upon closure of the implementation programme, the P3O capability is fully integrated into business as usual, marking the end of the transition phase." This differs from updating the Vision (A), producing the Blueprint (B), or capturing risks (C), which occur earlier. The 2013 edition emphasizes this transition to ensure operational sustainability, aligning with the P3O’s long-term role. This finalizes the implementation lifecycle.
[Reference: P3O® Foundation (2013) manual, Section 4.4.5, AXELOS. , ]
P3O-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"