What should a P3O recommend for 'must do' changes?
A.
Should be stopped immediately
B.
Must be completed before new changes are started
C.
Should be realigned to existing objectives
D.
Should be included in the portfolio to maintain business as usual
The Answer Is:
C
This question includes an explanation.
Explanation:
The Portfolio, Programme, and Project Office (P3O) is a framework that provides guidance on how to set up and maintain effective support structures for portfolio, program, and project management. A key function of a P3O is to ensure that all changes and initiatives within an organization are aligned with its strategic objectives.