Which is needed when getting the investment for a P3O?
A.
Independence of assurance services
B.
Defined portfolio of change
C.
Provision of secretariat services
D.
Recognition of the need for change
The Answer Is:
D
This question includes an explanation.
Explanation:
The P3O® Foundation (2013) manual indicates that recognition of the need for change is essential for securing P3O investment. Section 4.2.2 states, "Investment in a P3O requires recognition of the need for change to justify the business case and gain senior management support." This differs from assurance independence (A), portfolio definition (B), or secretariat services (C), which are operational aspects. The 2013 edition emphasizes this recognition as the foundation for funding approval, ensuring strategic alignment. This drives organizational commitment to the P3O model.
[Reference: P3O® Foundation (2013) manual, Section 4.2.2, AXELOS. , ]
P3O-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"